LINODE Fremont 的机房挂了,损失不少!。。。。。。

2015-05-30 13:36:16 +08:00
 t895

Datacenter Outage - Fremont
Update - Our upstream provider has provided a new estimated time to restoration of 11:30PM PDT.
May 30, 05:08 UTC
Update - Our upstream provider has provided a new estimated time to restoration of 10:00PM PDT.
May 30, 04:37 UTC
Update - At approximately 6:30PM PDT, the Fremont datacenter experienced a power utility outage. One out of eight generators also experienced an electromechanical failure. The estimated time to restoration is currently 9:30PM PDT. Linode has all hands on deck to get Linodes online as soon as power is restored.
May 30, 03:21 UTC
Update - We have received word from our colocation provider that there has been a power event in a section of the Fremont datacenter. The affected space is where a critical part of the datacenter network is located. The datacenter's electric provider is working with staff to restore power as soon as possible. Please watch this status page for further updates.
May 30, 02:25 UTC
Identified - We are aware of an issue within our Fremont datacenter and are investigating at this time. We will provide additional information as it becomes available.
May 30, 01:47 UTC

328 次点击
所在节点    VPS
1 条回复
t895
2015-05-30 13:38:52 +08:00
全部节点在Fremont,居然一下全挂了,我的妈妈咪啊。要死了!

这是一个专为移动设备优化的页面(即为了让你能够在 Google 搜索结果里秒开这个页面),如果你希望参与 V2EX 社区的讨论,你可以继续到 V2EX 上打开本讨论主题的完整版本。

https://www.v2ex.com/t/194900

V2EX 是创意工作者们的社区,是一个分享自己正在做的有趣事物、交流想法,可以遇见新朋友甚至新机会的地方。

V2EX is a community of developers, designers and creative people.

© 2021 V2EX